Supporting Indigenous Participation in Partnership with Australian Government

The Department for Infrastructure and Transport is committed to supporting Indigenous participation in our construction projects.

Indigenous employment and business participation rates are assessed for a range of projects undertaken in partnership with the Australian Government.

2023 results

Positive results achieved by construction contractors for our completed projects.

Rural Roads Package
Naracoorte Roundabouts upgrade

Our construction contractors achieved Indigenous participation of 6.8% on the completed Wimmera Junction Upgrades project:

  • Indigenous employment participation reached 4.2%. This exceeded the target of 3%.
  • The project also achieved 2.6% Indigenous business participation. This exceeded the target of 1.5%.

2022 results

Metro Intersection Upgrades
Goodwood, Springbank and Daws Road Intersection Upgrade
  • 12.1% of total employment hours were worked by Indigenous people. This exceeded the target of 2.2%.
  • Spend on Indigenous businesses was 4.65% of the total supplier spend on the project. The target was 1%.
Grand Junction, Hampstead and Briens Road Intersection Upgrade
  • Indigenous employment was 17.9% of total employment. The target was 2.2%.
  • 5.7% of total contract value was spent with Indigenous businesses. This exceeded the target of 0%.
Main North Road, Kings and McIntyre Roads Intersection Upgrade
  • Over 900 project hours were worked by Indigenous people.
  • 5% of the total project cost was spent with Indigenous businesses. This exceeded the target of 0%.
Main North Road and Nottage Terrace Intersection Upgrade
  • 6 Indigenous people worked on the project. This represents 2.8% of total employment. The target was 2.0%.
  • Information on spend with Indigenous businesses was not available. The performance against the 1% target was not verified.
Dublin Saleyard Access Upgrade

Indigenous employment for the Port Wakefield to Port Augusta Alliance was 7.8% of total employment during the construction period. The target was 5%.

South Eastern Freeway Pavement Rehabilitation: Tollgate to Crafers

Indigenous employment was 3.7% of total employment. The target was 2%.

Targeted Road Safety Works (TRSW) Program
TRSW ProgramEmployment participation
(% of hours worked)
Business participation
(% of total project budget)
Shoulder Sealing 8.0% 7.7%
Activated Safety Signage 0.8% 0.0%
Road Lighting 1.8% 0.3%
Variable Speed Limit Signs 18.4% 4.0%
Long Valley Road Mass Action 0.0% 0.0%
Audio-Tactile Line Marking 4.5% 0.4%
Safety Barrier 50.0% 0.5%
Overall TRSW progress to date5.5%1.0%
Targets3.0%3.0%
Road Safety Program works: Tranche 2
Project nameIndigenous hoursTotal hoursIndigenous participation (%)
Eyre Highway3,63425,60114.2%
Horrocks Highway3,52876,8934.6%
Barrier Highway8,11294,2738.6%
Stuart Highway1,09229,6473.7%
Riddoch HighwayContractor provided percentage only11.4%
Ngarkat Highway67249,7271.4%
Tod Highway6,47651,91212.5%
Birdseye Highway1,62715,35410.6%
Minlaton Road1,25427,0584.6%
Augusta Highway32020,7841.54%
Karoonda HighwayDue to delays in commencing the contract, indigenous participation was not measured in Tranche 2
Playford HighwayProject is being delivered by Kangaroo Island Council, so indigenous participation was not measured
Pages Flat RoadDue to the level of work delivered in Tranche 2, indigenous participation was not measured
Average26,715391,2496.8%
IPP Target

5.7%
Road Safety Program works: Tranche 3
Project nameIndigenous hoursTotal hoursIndigenous participation (%)
Eyre Highway3,64025,60114.22%
Horrocks Highway1,62618,8648.62%
Stuart Highway92722,5134.12%
Stuart Highway1,44123,0776.24%
Upper Yorke Hwy2,03027,7977.30%
Ngarkat Highway67251,8351.30%
Minlaton Rd1,23037,7133.26%
Karoonda Highway88422,0694.01%
Spencer Highway81420,6553.94%
Augusta Highway29720,9651.42%
Upper Yorke Hwy2,03027,7977.30%
Barrier Highway5,87749,21211.94%
Total21,468348,0986.17%
Target

5.70%
Regional North-South Freight Route

Our construction contractors achieved Indigenous participation of 6.6% on the completed Regional North-South Freight Route between Murray Bridge and the Sturt Highway.

  • Indigenous employment participation reached 5.9%, exceeding the target of 4%.
  • The project also achieved 0.7% Indigenous business participation by using an Indigenous labour hire company to source workers. While there wasn't a specific target set for this area, it's another positive outcome.

2021 results

Road Safety Program works: Tranche 1

Our results were very positive. We achieved an overall result of 7.7% participation. This surpassed the target of 5%.

Below is a breakdown of participation rates achieved on each of the roads under Tranche 1.

Project name Indigenous engagement (percentage of employment hours)
Eyre Highway 10.1%
Horrocks Highway* 5.7%
Barrier Highway 32.0%
Stuart Highway* 7.7%
Riddoch Highway 11.4%
Upper Yorke Road 7.7%
Ngarkat Highway 1.6%
Tod Highway 15.1%
Birdseye Highway 10.6%
Minlaton Road 1.7%
Karoonda Highway Not collected for Tranche 1
Playford Highway
Pages Flat Road
Average**7.7%
IPP Target5.7%

*Multiple contracts.

**The average of Indigenous employment hours across all contracts.