Temporary late night closures of the Outer Harbor and Grange rail lines
Saturday, 27 February 2021
The Department for Infrastructure and Transport advises there will be temporary late night closures of the Outer Harbor and Grange rail lines from Monday, 1 March to Thursday, 8 April, inclusive, with the exception of AFL match days.
Outer Harbor and Grange rail lines will be closed from 9pm until first service the following day to facilitate works at the interface between the Gawler and Outer Harbor/Grange lines as part of the Gawler Rail Electrification Project.
The following services have been cancelled, with substitute buses operating between Adelaide and Outer Harbor/Grange railway stations as closely as possible to the train timetable:
Adelaide to Outer Harbor | Outer Harbor to Adelaide | Adelaide to Grange | Grange to Adelaide | |
7:42pm | 8:28pm | 9:02pm | 9:31pm | |
8:12pm | 8:58pm | 10:02pm | 10:31pm | |
8:42pm | 9:28pm | 11:02pm | 11:31pm | |
9:12pm | 9:58pm | 12:02am | 12:31am | |
9:42pm | 10:28pm | |||
10:12pm | 10:58pm | |||
10:42pm | 11:28pm | |||
11:12pm | 11:58pm | |||
11:42pm | 12:28am | |||
12:12am | 12:58am |
The following Outer Harbor and Grange rail line services will be the last to operate each night before the closures:
- 7:12pm – Outer Harbor service departing Adelaide Railway Station
- 8:02pm – Grange service departing Adelaide railway Station
- 7:58pm – Outer Harbor service departing Outer Harbor
- 8:31pm – Grange service departing Grange.
Night closures will not occur while AFL matches are being hosted at Adelaide Oval. The Outer Harbor and Grange lines will remain open on the following nights:
- Saturday, 20 March: Adelaide Crows v Geelong (4:05pm)
- Saturday, 27 March: Port Adelaide v Essendon (4:05pm)
- Friday, 2 April: Adelaide Crows v Gold Coast (7:20pm)
- Friday, 9 April: Port Adelaide v Richmond (7:20pm)
For more information visit www.adelaidemetro.com.au.
The Department thanks commuters for their patience while these works are undertaken.
The Australian and South Australian Governments are jointly funding the $715 million electrification and modernisation of the Gawler rail line, which will deliver a faster, cleaner and more reliable service, delivering an electrified network through Adelaide from Gawler to Seaford.
The project, which is expected to be completed in late 2021, weather permitting, will support increased capacity and future growth for development along the rail corridor and in northern Adelaide.