Buildings - GC21 Managing Contractor

DISCLAIMER

These contracts have been designed for DIT's own use under the supervision of experienced professionals. While other organisations may use or reference these contracts, DIT assumes no responsibility whatsoever to any other party in any matter associated with these contracts. DIT does not represent or warrant that the use of these contracts is suitable for any non-DIT project. Any organisation seeking to use these contracts must rely on its own enquiries and bears all risks associated with the use of these contracts. By downloading any document from this site, you acknowledge and agree to DIT's Website Disclaimer.

Link to current version: 

GC21 General Conditions of Contract and Contract Information
Current update - version 9C, July 2024

Current Contract Amendments
ClauseComments
Clause 103

Payments – Clause 103.1

‘When given a Payment Claim by the Contractor, the Principal must within 10 Business Days’

Updated to ‘within 4 Business Days’.

Clause 103

Clause 103.5.1

‘the number of days specified in Contract Information item 53.C (or if no period is specified then 14 Calendar days) after expiry of the 10 Business Day period in clause 103.1; and’

Updated and replaced with:

‘the number of days specified in Contract Information item 53.C (or if no period is specified then 6 Business days) after expiry of the 4 Business Day period in clause 103.1; and’

Contract Information

Item 27 – Payment for Subcontract

Deleted:

‘Maximum period before payment for subcontract - 22 Business days’

And replace with:

‘Maximum period for payment under Subcontract – 10 Business Days’

Contract Information

Item 35 – Professional Indemnity Insurance

Minimum Cover - $5,000,000

Added:

‘And in any case, the above amount is per occurrence and in aggregate.’

Period of Cover

Added:

‘In addition to the above, where the Principal’s Novated Consultant has been novated to the Contractor, the Contractor must ensure that the Principal’s Novated Consultant continues to maintain the professional indemnity and other insurance required under the relevant agreement with the Principal’s Novated Consultant.

The Principal’s Novated Consultant Professional Indemnity Insurance requirement is a minimum of $XXXXXX’

Contract Information

Item 53 Payment date and method

C -Time for payment

’14 calendar days’ replaced with ‘6 Business Days’