Buildings - AS4300 - Early Contractor Involvement/TFP (ECI/TFP)

DISCLAIMER

These contracts have been designed for DIT's own use under the supervision of experienced professionals. While other organisations may use or reference these contracts, DIT assumes no responsibility whatsoever to any other party in any matter associated with these contracts. DIT does not represent or warrant that the use of these contracts is suitable for any non-DIT project. Any organisation seeking to use these contracts must rely on its own enquiries and bears all risks associated with the use of these contracts. By downloading any document from this site, you acknowledge and agree to DIT's Website Disclaimer


Link to current version: 
AS4300-1995 Special Conditions ECI
Current Update: Version 9B, July 2024

Current Contract Amendments
ClauseComments
Clause 9.2

Clause 9.2 – Subcontracting

Deleted:

‘(i)           payment provisions with the same times for payment as the payment provisions in AS 43031995 General conditions of subcontract, AS 25451993 Subcontract conditions or AS 41222000 General conditions of contract for engagement of consultants (as applicable); and’

And replace with:

‘security provisions as in AS 4303-1995 General conditions of subcontract, AS 2545-1993 Subcontract conditions or AS 41222000 General conditions of contract for engagement of consultants (as applicable)’;

Clause 9.2

Clause 9.2

Deleted:

‘subject only to such amendments and annexure entries as are necessary to reflect the conditions of this Contract.’

In the same Sub-Clause 9.2 – payment claim days have been updated to 10 Business Days as below –

“All subcontract conditions must include payment provisions which reflect that the Contractor must pay the subcontractor within (and no later than) 10 Business Days from payment claim

Clause 42.1

Clause 42.1 – Payment Claims, Certificates, Calculations and Time for Payment.

In the fourth paragraph, line 1,

deleted ‘within 14 days’ and replaced with ‘within 4 Business days’.

In the sixth paragraph,

  • Line 1, ‘within 28 days’ was deleted and replaced with ‘within 10 Business Days’
  • Line 2, ‘within 14 days’ was deleted and replaced with ‘within 6 Business Days’
  • Line 3.  'within 14 days' was deleted and replaced with 'within 10 Business Days'