Submission Times
TYPE OF WORK | REQUIRED ACCESS APPLICATION SUBMISSION TIME | APPROVAL LEVEL REQUIRED |
---|---|---|
Track possession necessitating the cancellation of train services due to a closure of a line or lines on a business day. | Typically 26 weeks | Minister of Transport and Chief Operating Officer |
Track possession necessitating the cancellation of train services due to a closure of a line or lines on a weekend or public holiday. | Typically 16 weeks | Minister of Transport and Chief Operating Officer |
Work requiring any temporary timetable change or change to rail plan. Eg to facilitate trains operating around the worksite either by bi-directional working or using alternative track. | 8 weeks | Manager Rail Operations |
Work requiring production of a new platform diagram. | 4 weeks | Manager Rail Operations |
Rail services are planned to be delayed for up to five (5) minutes | 21 days | Manager Rail Infrastructure Maintenance |
All other work | 21 days | Team Leader Network Access |