Update on South Eastern Freeway works this week

13 March 2015

Road uses are advised that this week’s road works along the South Eastern Freeway between the Stirling and Crafers interchanges have been revised to reduce impact on commuters.

The works are now expected to be completed earlier on Friday 20 March 2015, weather permitting. Details on the revised works below:

  • Tuesday 17 March
    Works will be carried out day and night between 9:30 am until 4:00 pm and 8:00 pm until 6:00 am the following day.

  • Wednesday 18 March
    Works will be carried out at night between 8:00 pm and 6:00 am the following day.

  • Thursday 19 March and Friday 20 March
    Works will be carried out between 9:30 am and 4:00 pm.

Speed restrictions will be in place during works. DPTI advises a 25 km/h speed restriction
will apply when workers are on site. Other speed restrictions and lane closures during non
peak times may apply subject to onsite conditions.

Thank you again to road users for your patience during these works.