Gawler East Link Road



Project Overview

The $59.97 million, Gawler East Link Road will provide local traffic with direct access to Main North Road without travelling through the Gawler Town Centre, reducing travel times, reducing the likelihood of crashes and minimising the vehicle emissions

caused by travel delays.

The project will provide flexibility for future growth of population, as well as allow full development of Gawler East. It will support economic activity in Gawler and enhance connectivity between current and future developments, commercial and school precincts, and create approximately 110 local construction employment opportunities through the life of the project in line with SA’s Industry Participation Policy.



The benefits of the GELR will include:

  • direct access for commuters to Main North Road without needing to travel through the Gawler Town Centre;
  • reduction in congestion and travel times on the local road network;
  • less likelihood of crashes in the Gawler Township;
  • reduction of vehicle emissions caused by travel delays;
  • creates access for potential future extensions off the link road.

Click here to view project plans.


Latest News


Main North Road

The Main North Road traffic changeover will commence end of November 2019 and will take approximately three months (weather permitting).
Traffic signals at both Main North Road Intersections will be operational mid-2020.

Potts Road

The Potts Road traffic changeover will commence mid December 2019 and will take approximately three months (weather permitting).
LED lights along Potts Road are to be installed and operational before Christmas.
The construction of the Potts Road roundabout is commenced December 2019.

Gawler One Tree Hill Road

The construction of the roundabout at Gawler-One Tree Hill Road is scheduled to commenced in November 2019.

Calton Road

The construction of the Calton Road roundabout is scheduled to commence by late December 2019.


All major service relocations are complete.

Minor relocations and property connections are ongoing and will be completed early 2020.


Project Timeframe

The Gawler East Link Road is due for completion late 2020.

Expected completion has been revised due to the inclusion of the Tulloch Road Intersection Upgrade, delivery of future services infrastructure (new sewer and water main), and additional earthworks within Springwood.

Gawler East Link Road progress photo (November 2019)


Further information

If you have any further enquiries or would like to register your interest in the project, please contact the project team:

Phone: 1300 282 939

Email: dpti.gelr@sa.gov.au.

To register to receive project information and updates, complete the online feedback form here and check the Latest News & Publications page regularly.


Latest News


Latest News


Project Plan


Fast Facts


Archive

Tulloch Road Intersection Upgrade

Progress photo of the Tulloch Road Intersection (October 2019)

Project Overview

The South Australian Government has committed $7.5 million to upgrade the Main North Road, Tulloch Road and Morrow Avenue Intersection, including duplication of Main North Road on approach and through the intersection.

The project will improve traffic flow, increase safety for drivers and pedestrians and better accommodate cyclists through the inclusion of new bicycle lanes.

28 jobs are expected to be supported over the life of the project.


The intersection upgrade includes:

  • upgrade of the Main North Road intersection with Tulloch Road and Morrow Avenue, including duplication of Main North Road on approach and through the intersection;
  • installation of traffic signals at the Main North Road / Tulloch Road / Morrow Avenue intersection including pedestrian crossings across all three roads;
  • construction of a new dedicated left turn lane from Main North Road into Tulloch Road;
  • construction of a new through lane from Tulloch Road into Morrow Avenue;
  • construction of new bicycle lanes on Main North Road through the intersection with Morrow Avenue and Tulloch Road;
  • construction and upgrade of existing footpaths;
  • upgrade of the Tulloch Road junction with Barnet Road. Barnet Road is also being changed to a cul-de-sac, at the junction of Barnet Road and Para Road, as part of the Gawler East Link Road Project; and
  • installation of LED road lighting to save energy and improve night time visibility.

Click here to view project plans.


Latest News

Tulloch Road

Service relocations and road widening have been completed.

New LED street lighting has been installed and will be operational shortly.

Main North Road

The Main North Road traffic changeover will commence early December 2019 and will take approximately three months (weather permitting).

Traffic signals at the Main North Road Intersection with Tulloch Road and Morrow Avenue are scheduled to be operational mid-2020.


Project Timeframe

The Tulloch Road Intersection Upgrade is due for completion late 2020.


Further information

If you have any further enquiries or would like to register your interest in the project, please contact the project team:

Phone: 1300 282 939

Email: dpti.gelr@sa.gov.au.

To register to receive project information and updates, complete the online feedback form here and check the Latest  ws & Publications page regularly.