Project Overview

North-South Corridor

North South Corridor MapNorth-South Corridor map

The North–South Corridor is one of Adelaide’s most important transport corridors. It is the major route for north and south bound traffic including freight vehicles running between Gawler and Old Noarlunga, a distance of 78 kilometres, and is comprised of four road links:

  • Northern Expressway from Gawler to Port Wakefield Road
  • Northern Connector from Port Wakefield Road to Port River Expressway
  • Main South Road from Port River Expressway to Southern Expressway; and
  • Southern Expressway from Darlington to Old Noarlunga.

The Australian Government has announced its intention to upgrade the North–South Corridor over ten years and, together with the South Australian Government, has committed to construct the $754.5 million Darlington Upgrade Project. The Australian Government will contribute $603.6 million and the State Government $150.9 million for the Darlington Upgrade Project.

The upgraded North–South Corridor will provide a series of strategic free-flowing road links to connect the rapidly expanding industrial and residential growth areas in the north and the south, to provide new opportunities for economic development.

The current roadway isn’t capable of handling projected growth and the number of vehicles that need to use the road or the size of the freight carriers travelling along it. In response, Australian and South Australian governments are expanding the route by creating a dedicated non-stop North-South Corridor with a program underway to eliminate the worst bottlenecks.

To date, 44 km of the North–South Corridor has been completed. New road links have been built between Gawler and Port Wakefield Road (Northern Expressway), Regency Road and the Port River Expressway (South Road Superway) and between Bedford Park and Old Noarlunga (Southern Expressway duplication). Traffic flow along and across the route has also improved with the construction of the Gallipoli Underpass and the Glenelg Tram Overpass.

Project Timelines

Project phaseActivitiesDate
Concept planning and investigations
  • Development of possible road options
  • Stakeholder and community engagement
  • Preliminary field investigations
  • Initiate property acquisition
December 2013 to October 2014
Pre-construction
  • Ongoing property acquisition
  • Property demolition
  • Environmental and other approvals
  • Procurement (award Design and Construct Contract)
  • Early works – service relocations and local/arterial road and intersection upgrades on alternative/parallel routes
  • Ongoing community and stakeholder engagement
October 2014 to late 2015     
Construction
  • Release of the Project Assessment Report
  • Construction
  • Ongoing community and stakeholder engagement and other activities
Late 2015 to mid-2020
Post-construction
  • Operation and maintenance
mid-2020 onwards