DPTI Capital Works Program


DPTI Forward Work Plan

On 3 August 2017, the Department held a briefing session with industry to provide information on our upcoming capital works projects, including proposed delivery models. A copy of the industry briefing presentation can be downloaded here.

At this briefing, the Chief Executive launched DPTI’s Forward Work Plan 2021 (PDF, 3050 KB). The session also outlined roles for construction contractors, designers, project management and contract management organisations who partner with the Department on the delivery of the future program of works.

DPTI Capital Initiatives Delivery Program

What does this mean for industry?

The delivery approach aims to:

  • Translate funding commitments to contract quicker.
  • Harness both DPTI and market expertise to deliver DPTI’s capital works, including private sector innovation.
  • Reward industry to deliver key project outcomes that realise DPTI's Strategic Objectives
  • Encourage the private sector to set up in SA and create jobs.

Program of works

Tender opportunities, dates and key contacts associated with the DPTI Capital Initiatives program are provided in the following table:

Procurement Program

Indicative Program Value ($m)

Key DPTI Contact

Tender timeframes (indicative)

Start

Award

Adelaide Metropolitan works program - design and construction

18

tim.wheaton@sa.gov.au

21 September 2017

21 December 2017

Adelaide Metropolitan works program - design

0.5

paul.wingent@sa.gov.au

19 September 2017

13 October 2017

Adelaide Metropolitan works program - construct only

7

tim.wheaton@sa.gov.au

23 October 2017

22 December 2017

Regional bridges program - Lobethal freight Route, Inverbrackie Bridge, Sturt Highway Bridges and regional bridges - design and construction

30

stephen.goldfinch@sa.gov.au

7 September 2017

19 December 2017

Regional works program - Shoulder Sealing, Truck Parking Bays  and associated works - construct only

30

craig.eckermann@sa.gov.au

18 September 2017

17 November 2017

Regional works program - Limestone Coast Intersection Upgrades - construct only

4

craig.eckermann@sa.gov.au

11 September 2017

19 October 2017

Regional works program - road re-sheeting - construct only

4

craig.eckermann@sa.gov.au

15 September 2017

26 October 2017

Port Bonython Jetty Refurbishment

5

andy.kitchen@sa.gov.au

7 October 2017

7 December 2017

Jetty refurbishments - Henley Beach Jetty, Semaphore Jetty, Cowell

3.5

andy.kitchen@sa.gov.au

7 October 2017

7 December 2017

Public Transport Projects Alliance (incl Oaklands Rail Crossing, Port Dock Railway Line and Park'n'rides)

205

peter.newbold@sa.gov.au

24 August 2017

20 December 2017

Gawler Electrification - Stage 1

152

darren.schulz@sa.gov.au

16 September 2017

18 December 2017

Gawler East Link Road

55

matthew.hogan@sa.gov.au

12 September 2017

19 December 2017

OCC relocation - control room fitout and related construction works

N/A

david.rushton@sa.gov.au

1 September 2017

22 December 2017

Parafield Park n Ride

4

james.irving@sa.gov.au

8 September 2017

5 February 2018

Adelaide Oval - security bollard upgrade

4

michael.rander@sa.gov.au

6 September 2017

13 October 2017

PMCA Panel - establishment of PMCA panel contract with consultants

N/A

Joseph Glatter & Tim Champion

TBA

TBA

For further information, please email Dpti.communityrelations@sa.gov.au.